Owner : National Chemical Fertilizer Company (SABIC)
Main Contractor : Sinopec Engineering Group Saudi Co
Scope : Civil Work, Erection and Installation of Structural Steel, Equipment (rotating and static) and Pipes Work, Painting and Insulation work, Electrical and Instrument Installation and Temporary Facilities Work
Max Mobilization Manpower : 200 People
Date : 2Sep/2018 To Apr-2020
GAS PHASE-9 Project
GAS PHASE-9 Project
Owner : National Industrial Gases Company (SABIC)
Main Contractor : TECNICAS REUNIDAS
Scope : Train-1 Erection and Installation of Structural Steel, Equipment (rotating and static) and Pipes Work. Package-1 Piping Support Prefabrication
Max Mobilization Manpower : 650 People
Date : May-2017 To Oct-2019
FADHILI Gas Program (FGP) Project
FADHILI Gas Program (FGP) Project
Owner : National Industrial Gases Company (Aramco)
Main Contractor : TECNICAS REUNIDAS
Scope : Train-1 Erection and Installation of Structural Steel, Equipment (rotating and static) and Pipes Work. Package-1 Piping Support Prefabrication
Max Mobilization Manpower : 650 People
Date : May-2017 To Oct-2019
Mechanical Construction Work For LIWA PROJECT
Mechanical Construction Work For LIWA PROJECT
Owner : ORPIC PLASTICS LLC
Main Contractor : CB and I-CTCI B.V.
Scope : Erection and Installation of Structural Steel, Equipment (rotating and static) and Pipes Work, Painting and Insulation work, Pre-Commissioning Work and Temporary Facilities Work
Max Mobilization Manpower : 300 People
Date : Dec-2017 To May-2019
SAMAC MMA/PMMA PLANT PROJECT
SAMAC MMA/PMMA PLANT PROJECT
Owner : Saudi Methacrylates Company (SABIC)
Main Contractor : CTCI Arabia Ltd
Scope : Erection and Installation of Structural Steel, Equipment (rotating and static) and Pipes Work Painting and Insulation work, Electrical and Instrument Work
Max Mobilization Manpower : 220 People
Date : Feb-2016 To May-2017
Sulphuric Acid Plant and Power Plant
Sulphuric Acid Plant and Power Plant
Owner : Saudi Arabia Mining Company
Main Contractor : FLOUR Arabia Ltd.
Scope : Train-1 Erection and Installation of Structural Steel, Equipment and Pipes Work. Electrical and Instrument Installation
Max Mobilization Manpower : 600 People
Date : Nov-2014 To Jun-2016
Utilities and Infrastructure (U & I)
Utilities and Infrastructure (U& I)
Owner : Saudi Arabia Mining Company
Main Contractor : FLOUR Arabia Ltd.
Scope : Ground Piping Installation
Max Mobilization Manpower : 240 People
Date : Jun-2015 To Jul-2016
Gizan Refinery & Terminal Project
Gizan Refinery & Terminal Project
Owner : Saudi Arabian Oil Company
Main Contractor : SK Engineering & Construction Co.Ltd.
Scope : Train-1 Erection and Installation of Structural Steel, Equipment and Pipes Work.
Max Mobilization Manpower : 360 People
Date : Oct-2015 To Dec-2017
Yanbu Export Refinery Project
Yanbu Export Refinery Project
Owner : Saudi Arabian Oil Company
Main Contractor : SK Engineering & Construction Co.Ltd
Scope : Erection and Installation of Structural Steel, Equipment and Pipes Work.
Max Mobilization Manpower : 320 People
Date : Jul-2011 To Jan-2014
Natural Detergent Alcohol (NDA) Project
Natural Detergent Alcohol (NDA) Project
Owner : Saudi Kayan Petrochemical Company
Main Contractor : SINOPEC - SEG
Scope : Erection and Installation of Structural Steel, Equipment and Pipes Work. Electrical and Instrument Work
Max Mobilization Manpower : 350 People
Date : Dec-2011 To Nov-2013
AMINES Project
AMINES Project
Owner : Saudi Kayan Petrochemical Company
Main Contractor : CTCI Arabia Ltd.
Scope : Erection and Installation of Structural Steel, Equipment and Pipes Work. Electrical and Instrument Work
Max Mobilization Manpower : 420 People
Date : Aug-2010 To Dec-2011
Prot Area and Tank Farm Project
Prot Area and Tank Farm Project
Owner : Saudi Kayan Petrochemical Complany
Main Contractor : FLOUR Arabia Ltd.
Scope : Erection and Installation of Structural Steel, Equipment and Pipes Work. Electrical and Instrument Work
Max Mobilization Manpower : 420 People
Date : Feb-2009 To May-2010
6” Hydrogen Gas Pipe Line Project
6” Hydrogen Gas Pipe Line Project
Owner : Petrokemya Petrochemical Company
Main Contractor : SINOPEC - SEG.
Scope : Erection and Installation of Structural Steel, Equipment and Pipes Work. Electrical and Instrument Work
Max Mobilization Manpower : 120 People
Date : Dec-2011 To May-2012
YANSAB Butene/BTX (BBTX) project
YANSAB Butene/BTX (BBTX) project
Owner : Saudi Arabia Basic Industries Corporation
Main Contractor : Foster Wheeler (FW) & SCM Co.(Shaw)
Scope : Erection and Installation of Structural Steel, Equipment and Pipes Work. Electrical and Instrument Work
Max Mobilization Manpower : 300 People
Date : Jan-2008 To Jun-2009
YANSAB Polyolefin Project
YANSAB Butene/BTX (BBTX) project
Owner : Saudi Arabia Basic Industries Corporation
Main Contractor : SINOPEC - SSEC
Scope : Erection and Installation of Structural Steel, Equipment and Pipes Work. Electrical and Instrument Work